By the time the house is on display in October 2009, Virginia Tech will have been working on the design and building of the 2009 house for almost two years! Follow the progress below.

APRIL 2009

april 2009 | welding beams
  • Slab ground to a polished finish
  • Mechanical closet wall finishes installed
  • Mechanical team finished the HVAC layout
  • Steel water pump rack fabricated and installed
  • Steel beams for Eclipsis System welded to frame
  • LUMENHAUS website schematic designs and site architecture created with MODEA